针对特高压注入后直流闭锁故障时大功率失去的问题,提出一种备用辅助服务下弥补大功率缺额,进行机组组合优化调度的方法。通过仿真算例验证备用辅助服务参与下的机组组合成本有效降低。结果表明,方法对电力经济调度优化有重要意义,同时对于提高发电厂提供辅助服务的积极性,促进主能量和辅助服务的均衡协调供应也有着重要意义。
Considering loss of high power in case of DC blocking fault occurring after UHV injection,a method for compensation of high power vacancy under standby auxiliary services and for optimized scheduling of unit combination was presented in this paper.Simulation examples verified that the unit combination cost was reduced greatly with participation of standby auxiliary service.The results indicated that the proposed approach could be of great significance to the optimization of power economic dispatch.In the meantime,it was also important for the enhancement of the initiative of power plants to provide auxiliary services and for the promotion of balanced and coordinated supply of main energy and auxiliary services.
作者
李莉
李智
鲍冠南
刘航航
廖大鹏
胡婧雯
Li Li;Li Zhi;Bao Guannan;Liu Hanghang;Liao Dapeng;Hu Jingwen(State Grid Shandong Electric Power Co.,Ltd., Jinan Power Supply Co., Jinan Shandong 250012, China;State Grid Shandong Electric Power Co.,Ltd., Jinan Shandong 250001, China;Hangzhou WR Power Technology Co., Ltd., Hangzhou Zhejiang 310000, China)
出处
《电气自动化》
2020年第6期62-66,共5页
Electrical Automation
基金
国网山东省电力公司资助科技项目:特高压交直流混联受端电网安全风险预警和控制决策技术研究-课题4:特高压交直流受端电网调度计划智能管控及优化决策技术(52060118015Y)。
关键词
特高压
备用辅助服务
机组组合
成本
优化调度
UHV
standby auxiliary service
unit combination
cost