某大跨钢结构管桁架工程施工技术研究 被引量:5

Construction technology of a large-span steel structure pipe truss project
下载PDF
导出
摘要 重庆融创茂娱雪乐园场馆为跨度97 m的大跨度空间管桁架钢结构,拼装工艺、相贯结构复杂,施工条件较差,质量要求高,在实际施工中,采用地面分段拼装,通过设置临时支撑胎架进行分段吊装再高空对接,最后整体卸载的安装方式,通过合理的施工部署和质量控制,成功按时保质保量的完成了该场馆的钢结构安装工作。 Chongqing Rongchuang Mao Snow Park is a steel structure with a span of 97 m,which is made up of large-span spatial tube truss.The assembling technology and intersecting structure are complex,the construction conditions are poor and the quality requirements are high,the steel structure of the stadium was successfully installed in time,quality and quantity by setting up temporary supporting frame to be lifted and then connected at high altitude.
作者 黄伟 白海 王虎 Huang Wei;Bai Hai;Wang Hu(MCC(Shanghai)Steel Structure Technology Co.,Ltd.,Shanghai 200941,China)
出处 《山西建筑》 2020年第24期80-82,共3页 Shanxi Architecture
关键词 管桁架 分段拼装 分段吊装 支撑胎架 整体卸载 pipe truss segmentation assembling segmentation hoisting support frame overall unloading
  • 相关文献

参考文献3

二级参考文献15

共引文献23

同被引文献22

引证文献5

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部