摘要
针对目前粪便处理中存在的主要问题,介绍某设计规模为100 m^3/d粪便处理厂的污水处理设计,包括污水处理工艺流程、建构筑物及设备设计参数等,并对5个月的工程调试数据进行分析,出水水质达到GB 8978—1996污水综合排放标准中的三级标准及当地污水厂进厂标准。
For the main existed problems in fecal treatment at present,the sewage treatment design of a sewage treatment plant of 100 m3/d design scale was introduced,which included sewage treatment technological process,construction and equipment design parameters,et al.And the engineering commissioning data of 5 months was analyzed,the quality of effluent reached the three-level standard of Integrated Wastewater Discharge Standard(GB 8978—1996)and the entered standards of the local sewage plant.
作者
李清
赵卫兵
张勇
朱小明
张伦
马星辰
Li Qing;Zhao Weibing;Zhang Yong;Zhu Xiaoming;Zhang Lun;Ma Xingchen(Sinomach TDI International Engineering Co.Ltd.,Beijing 100086)
出处
《环境卫生工程》
2020年第5期16-20,共5页
Environmental Sanitation Engineering
关键词
粪便污水
固液分离
絮凝脱水
生物处理
脱氮除磷
fecal sewage
solid-liquid separation
flocculation dehydration
biological treatment
nitrogen and phosphorus removal