摘要
针对邮轮薄板平面分段流水线计划管控需求问题,以国内某船厂薄板流水线的实际工位布置为例,运用网络计划方法编制流水线网络图,计算流水线关键路径及关键工位,利用时标网络图和实际进度前锋线计算分析流水线计划的纠偏措施,保证流水线高效运转。
The problem of cruise ships sheet metal assembly line was investigated.Taking the actual arrangement of thin plate assembly line of a shipyard in China as an example,the method of network planning was used to compile the network diagram of the assembly line,and calculate the critical path and key location of the assembly line.The time-coordinate network diagram and the forward line of process were applied to analyze the corrective measure of the assembly line plan,so as to assure the assembly line operate efficiently.
作者
朱安庆
余逸
王炬成
ZHU An-qing;YU Yi;WANG Ju-cheng(School of Naval Architecture and Ocean Engineering, Jiangsu University of Science and Technology, Zhenjiang Jiangsu 212003, China;Jiangsu Modern Shipbuilding Technology Co., Ltd., Zhenjiang Jiangsu 212003, China)
出处
《船海工程》
北大核心
2020年第5期49-53,共5页
Ship & Ocean Engineering
基金
工信部高技术船舶项目(工信部装函[2018]473号)。
关键词
邮轮
计划管理
薄板流水线
网络计划
cruise ships
plan management
sheet metal assembly line
network planning