摘要
针对部分煤矿多期三维地震勘探工作出现三维地震资料衔接上的问题,本文以义能煤矿项目为例,通过对以往三维地震资料进行整合处理与重新解释,很好地解决了这个问题,为其他煤矿提供一些借鉴价值。
In view of the problems of three-dimensional seismic data convergence in multi-phase seismic exploration in some coal mines,this paper takes the Yineng Coal Mine project as an example,through the previous 3D seismic data integration processing and reinterpretation,solves this problem well,provides some reference value for other coal mines.
作者
林全章
Lin Quanzhang(Geophysical Survey Team of Shandong Coalfield Geological Bureau,Shandong Ji'nan 250104)
出处
《山东煤炭科技》
2020年第9期170-172,共3页
Shandong Coal Science and Technology
关键词
地震勘探
整合处理
整体解释
断裂构造
seismic prospecting
integrated processing
overall interpretation
fault structure