由于巴西电网自身特许经营体制及电力私有化体制的特点,巴西电网设计过程与国内存在较大差异。梳理了该工程控保设计部分的主要差异,并进行了对比分析,为后续工程提供了参考和借鉴。
Due to the characteristics of the Brazilian power grid′s own franchise system and power privatization system,the design process of the Brazilian power grid is quite different from that in China.The main differences of the control and security design part of the project were sorted out,and a comparative analysis was conducted to provide reference and reference for subsequent projects.
作者
贺磊
谢龙
魏来
HE Lei;XIE Long;WEI Lai(Central Southern China Electric Power Design Institute,Wuhan 430071,China)
出处
《电工技术》
2020年第13期128-129,133,共3页
Electric Engineering
基金
国家重点研发计划资助项目(编号2016YFB0900800)。
关键词
巴西
±800
kV特高压直流工程
控保
电气二次
工程设计
Brazil
±800kV UHV DC project
control and protection
electrical secondary
engineering design