轻型井点与管井组合降水在深基坑工程中的应用 被引量:4

The Application of Combination of Light Well Point and Tube Well Precipitation in Deep Foundation Pit Engineering
下载PDF
导出
摘要 以郑州市郑东新区康庄社区A区深基坑工程为例,论述了管井与轻型井点组合降水施工工艺及方法,该降水方法即满足了深基坑的有效降水深度,又解决了基坑坡面因滞水层导致的渗水涌砂问题,保证了基坑的安全稳定和土方开挖等施工需要。 Taking the deep foundation pit project in zone A,Kangzhuang community,Zhengdong new district,Zhengzhou city as an example,this paper discusses the construction technology and method of combined dewatering of pipe well and light well point.The combination of two types of precipitation not only satisfies the effective dewatering depth of deep foundation pit,but also solves the problem of seepage and sand gushing caused by stagnant water layer on the slope of foundation pit,thus ensuring the safety and stability of foundation pit and the construction needs of earthwork excavation.
作者 许俊朋 张洪欣 梁宁 XU Jun-peng;ZHANG Hong-xin;LIANG Ning(No.3 Institute of Geological&Mineral Resources Survey of Henan Geological Bureau,Zhengzhou 451464,China;Henan Provincal Non-Ferrous Metals Geological Mineral Resources Resources,Zhengzhou 451464,China)
出处 《工程建设与设计》 2020年第12期47-48,共2页 Construction & Design for Engineering
关键词 深基坑 管井 轻型井点 滞水层 deep foundation pit tube well light well point stagnant water layer
  • 相关文献

参考文献2

二级参考文献7

共引文献14

同被引文献19

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部