钢管混凝土拱桥拱肋混凝土灌注顺序研究

Study on Pouring Sequence of Arch Rib Concrete of Concrete Filled Steel Tube Arch Bridge
下载PDF
导出
摘要 针对三拱肋钢管混凝土桥拱肋混凝土灌注顺序进行分析,研究拱肋混凝土的灌注顺序对施工全过程中拱肋内力、应力和位移的影响,以确定合理的灌注顺序,保证混凝土灌注安全可控。研究结果显示:先灌注下弦管再灌注上弦管不易造成混凝土开裂;先灌注边拱肋再灌注中拱肋产生的混凝土拉应力要小于先灌注中拱肋再灌注两侧边拱肋产生的拉应力。 Based on the analysis on the pouring sequence of the arch rib concrete of a three arch rib concrete flled steel tube bridge,the influence of pouring sequence of arch rib concrete on the internal force,stress and displacement of arch rib in the whole construction process is studied,so as to determine the reasonable pouring sequence and ensure the safety control of concrete pouring.The results show that:it is not easy to crack the concrete by pouring the lower chord first and then the upper chord;the concrete tensile stress produced by pouring the side arch rib first and then the middle arch rib is less than that produced by pouring the middle arch rib first and then the side arch rib at both sides.
作者 徐清 XU Qing(China Gezhouba Group Construction Engineering Co.,Ltd.,Kunming,Yunnan 650200,China)
出处 《建筑施工》 2020年第5期816-819,共4页 Building Construction
关键词 钢管混凝土拱桥 拱肋混凝土 灌注顺序 应力 concrete flled steel tube arch bridge arch rib concrete pouring sequence stress
  • 相关文献

参考文献5

  • 1余强..钢管砼拱桥拱肋安装与管内砼灌注应力调整研究[D].重庆交通大学,2017:
  • 2陈宝春著..钢管混凝土拱桥[M].北京:人民交通出版社,2007:898.
  • 3王铁梦著..工程结构裂缝控制 “抗与放”的设计原则及其在“跳仓法”施工中的应用[M].北京:中国建筑工业出版社,2007:186.
  • 4吴何..钢管混凝土拱肋混凝土灌注工序研究[D].西南交通大学,2017:
  • 5顾箭峰..钢管混凝土拱桥灌注混凝土仿真分析研究[D].长安大学,2012: