无锡地铁3号线一期工程重叠盾构区间施工技术 被引量:3

Construction Technology of Overlap Shield Section for Phase Ⅰ of Wuxi’s Metro Line 3
下载PDF
导出
摘要 无锡地铁3号线一期工程长~机区间与新梅出入段区间在一定范围内形成重叠段隧道,采用下方盾构隧道先行施工,后上方盾构隧道施工的顺序,在地面加固重叠段下方隧道,夹层土注浆加固,下方隧道内临时钢支架安装,严格控制盾构掘进参数,合理选用同步注浆材料,科学监测的方法,成功穿越重叠段。 In the first phase of the subway line 3,the overlap section tunnel is formed within a certain range between the Chang-Ji interval and the Xin-Mei entry and exit section.The shield tunnel is first constructed under the shield tunnel,and the tunnel below the overlap section is reinforced on the ground.The interlayer soil is reinforced by grouting,and the temporary steel bracket in the lower tunnel is installed.The shield tunnelling parameters are strictly controlled and the same is chosen reasonably.The step grouting material and scientific monitoring method have successfully crossed the overlapping section.
作者 李迎春 魏善林 LI Ying-chun;WEI Shan-lin(Wuxi Metro Group Co.,Ltd,Wuxi Jiangsu 214100China;Jiangsu Zhongshe Group Co.,Ltd,Wuxi Jiangsu 214072 China)
出处 《江苏建筑》 2020年第2期66-68,共3页 Jiangsu Construction
基金 江苏省建设系统科技项目(2018ZD254)。
关键词 重叠段 盾构隧道 加固 监测 overlapping section shield tunnel reinforcement monitoring
  • 相关文献

参考文献3

二级参考文献12

共引文献149

同被引文献6

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部