摘要 明挖法和盖挖法在隧道过河段施工中均有各自优势。以兴泉铁路某隧道过河段施工为例,通过两种施工方法的比较,分析了明挖存在的问题和容易产生的不利后果,优选采用拱盖盖挖法施工,并围绕拱盖设计、施工步骤、施工注意事项、取得效果等阐述了拱盖盖挖法施工。结果表明,通过过程控制,拱盖盖挖法施工在工期、安全、成本、质量等方面取得积极的效果,凸显了该方法的施工优势,为类似工程施工提供了借鉴。 Open excavation method and cover excavation method both have their own advantages in tunnel crossing construction.Through the comparison of two construction methods in the construction of a tunnel crossing the river in XingquanRailway,the problems existing and the adverse consequences in open excavation method is analyzed and cover excavation methodis adopted,focusing on arch cover design,construction steps,construction regulations and the effects.Through the process control,the arch cover method achieved positive results in terms of time limit,safety,cost and quality with its constructing advantages,providing reference for similar engineering construction.
作者 张海波 ZHANG Hai-bo(Tunnel Engineering CO.,LTD.,China Railway 18th Bureau Group,Chongqing 400700,China)
出处 《浙江水利水电学院学报》 2020年第2期58-61,共4页 Journal of Zhejiang University of Water Resources and Electric Power
关键词 隧道 过河段 拱盖盖挖 tunnel river crossing arch cover excavation method
  • 相关文献

参考文献12

二级参考文献59

共引文献108

同被引文献8

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部