摘要
文章依据配电网35kV变电站功率因数考核要求,提出一种新的变电站VQC模糊控制策略,该策略在传统五区图的基础上增加功率因数作为输入量,并利用MATLAB搭建仿真模型,通过仿真结果分析,验证控制策略的优越性和可行性。
According to the requirements of power factor assessment of 35kV substation in distribution network,a new fuzzy control strategy of VQC in substation is proposed.Based on the traditional five zone diagram,the power factor is added as the input,and a simulation model is built with MATLAB.Through the analysis of simulation results,the superiority and feasibility of the control strategy are verified.
作者
王庆坤
张宝杰
任俊业
吕孝臣
Wang Qingkun;Zhang Baojie;Ren Junye;Lv Xiaochen(Electrical Engineering Department Of Binzhou University,Binzhou,Shandong 256603;STATE GRID SISHUI POWER SUPPLY COMPANY,Jining,Shandong 273200)
基金
滨州学院2019年度大学生研究训练计划(SRTP)项目(SRTP2019227)
关键词
变电站
模糊控制
五区图
substation
fuzzy control
five-zone map