摘要
以天津市金钟河大街三线换乘枢纽站的工程为例,采用数值计算和现场监测相结合方法,重点分析和研究复杂条件下换乘车站的“顺逆结合”、同步实施、同步开挖方案的可行性,从而达到既缩短总工期又降低工程成本的双赢效果。这种同步实施方案可为后期相似工程设计、施工提供参考。
Taking the project of Jinzhonghe Ave.three-line transfer hub station in Tianjin as an example,using the method of numerical calculation&on-site monitoring,this paper focuses on the analysis&research of the feasibility of the combination of forward and reverse,synchronous implementa tion&synchronous excavation scheme of transfer station under complex conditions,so as to achieve the win-win effect of reducing the total construction period&the project cost.This synchronous implementation scheme can provide reference for similar engineering design&construction in later stage.