摘要
为控制施工质量、加快施工进度,在白鹤滩水电站库区东川区象鼻岭防护工程填筑碾压过程中,采用了智慧碾压技术,在主要碾压设备上安置了信息化控制平板,实现了对堤防填筑施工的全过程监控,保证了工程的质量与安全。
In order to control the construction quality and speed up the construction progress,the intelli gent rolling technology was adopted in the filling and rolling of Dongchuan Xiangbiling protection proj ect of Baihetan hydropower station.Information control panels were installed on the main rolling equip ment,thus the whole-process monitoring of embankment filling construction was realized,ensured the quality and safety of the project.
作者
张炳初
曾章波
ZHANG Bingchu;ZENG Zhangbo(Zhejiang Huadong Engineering Construction and Management Corporation Limited)
出处
《大坝与安全》
2019年第6期38-41,共4页
Dam & Safety
关键词
智慧碾压
堤防
填筑
intelligent rolling
embankment
filling