暗挖隧道爆破开挖质量控制研究 被引量:2

Study on quality control of blasting excavation of underground tunnel
下载PDF
导出
摘要 暗挖隧道爆破开挖施工过程中,保持良好的开挖质量,无论从成本控制角度还是工期角度,都具有重要的意义。以深圳地铁8号线望基湖停车场入场线隧道为例,对影响隧道开挖质量的条件展开分析,通过运用光面爆破技术以及加强现场施工质量管理等手段,最大程度的减少超欠挖,有效的提升了隧道的开挖质量,可为同类隧道开挖施工提供借鉴。 In the process of blasting excavation,it is of great significance to maintain a good excavation quality in terms of cost control and time limit.Taking Wangjihu parking lot entrance line tunnel of Shenzhen metro line 8 as an example,this paper analyses the conditions affecting the quality of tunnel excavation.By using smooth blasting technology and strengthening the quality management of site construction,it can minimize overbreak and underbreak,effectively improve the quality of tunnel excavation,and provide reference for similar tunnel excavation construction.
作者 严国庆 Yan Guoqing(China Railway Shisiju Group Corporation Tunnel Engineering Co.,Ltd.,Jinan 250000,China)
出处 《山西建筑》 2020年第1期131-133,共3页 Shanxi Architecture
关键词 暗挖隧道 爆破 开挖 质量控制 underground excavation blast excavation quality control
  • 相关文献

参考文献10

二级参考文献45

共引文献126

同被引文献13

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部