巴岳山隧道受煤矿采动影响分析 被引量:2

Analysis of the Effect of Underground Coal Mining on the Bayueshan Tunnel
下载PDF
导出
摘要 受新生、昌荣两煤矿开采影响,渝蓉高速公路巴岳山隧道部分路段出现裂缝及两帮掉块等现象。为掌握隧道受开采影响状况,文章基于概率积分法计算了各阶段地下开采引起的地表移动与变形值,并以隧道左线为例,分析了隧道损坏的成因,以及煤炭资源全部开采后隧道左线可能受损情况,提出了可供隧道维护及保障安全的工程措施建议。预计结果与隧道损害情况接近,因此概率积分法可以用于隧道受采动影响分析。 Affected by the mining of Xinsheng coal mine and Changrong coal mine,some cracks and chip off-falling occur at the Bayueshan tunnel of Chongqing-Chengdu expressway.In order to understand the impact of coal mining on the tunnel,the tunnel displacement and deformation caused by underground mining in different stages are calculated with probability integral method,the causes of tunnel and pavement damages and deformation of the left tube after full mining of coal resources are analyzed by taking the left tunnel tube as an example,and the recommended measures for tunnel maintenance and safety are proposed.The predicted results are basically consistent with the actual conditions of tunnel and pavement damages.
作者 孙浩轩 李培现 崔希民 姚德华 肖武 SUN Haoxuan;LI Peixian;CUI Ximin;YAO Dehua;XIAO Wu(China University of Mining and Technology(Beijing),100083;China Railway Fifth Survey and Design Institute Group Co.,Ltd,Beijing 102600;School of Public Affairs,Zhejiang University,Hangzhou 310058)
出处 《现代隧道技术》 EI CSCD 北大核心 2019年第6期99-106,120,共9页 Modern Tunnelling Technology
关键词 隧道损伤 采动影响 开采沉陷 概率积分法 保护措施 Tunnel damage Mining effect Mining induced subsidence Probability integral method Protective measures
  • 相关文献

参考文献13

二级参考文献81

共引文献162

同被引文献15

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部