下穿高速公路箱涵顶进施工控制措施及监测分析 被引量:5

Control measures and monitoring analysis of jacking construction of box culvert under expressway
下载PDF
导出
摘要 以某工业园区新建道路下穿高速公路项目为依托,进行箱涵顶进过程中的施工监测研究。针对该工程特点,提出了几项减少箱涵顶进阻力和控制沉降位移的措施以及顶进过程监测方案。经现场监测数据结果表明,该箱涵顶进过程箱涵姿态控制较好,对路面的位移和沉降影响较小。 Based on the project of a new road crossing expressway in an industrial park,the construction monitoring of box culvert jacking is studied.According to the characteristics of the project,several measures for reducing jacking resistance and controlling settlement displacement of box culvert and monitoring scheme for jacking process are put forward.The field monitoring data show that the attitude control of the box culvert during jacking is good,and the influence on the displacement and settlement of the road surface is small.
作者 刘恒 曾芙霞 何奎元 Liu Heng;Zeng Fuxia;He Kuiyuan(School of Railway Engineering,Hunan Technical College of Railway High-speed,Hengyang 421002,China)
出处 《山西建筑》 2019年第20期104-105,共2页 Shanxi Architecture
基金 衡阳市科技计划项目(2016KG57)《大断面长箱涵顶进监测技术和沉降控制措施的研究》
关键词 箱涵顶进 控制措施 沉降监测 位移监测 box culvert jacking control measures settlement monitoring displacement monitoring