上湾煤矿特大型贯通测量实践与分析 被引量:5

Practices and analysis on ultra long holing-through survey in Shangwan Mine
下载PDF
导出
摘要 为了保证贯通精度,贯通前进行贯通误差预计;巷道掘进过程中采用两次独立观测(导线、陀螺),提高观测精度。结果表明:通过测量仪器、观测手段、数据处理方法的选取,可以确保一井内的精准贯通,此次14 km贯通工程精度达到水平重要方向贯通误差-0.182 m、高程贯通误差0.215 m。 Frist, in order to ensure an accurate, in the paper, the through forecast error was got. Secondly, in the heading process of the mine roadway, two independent survey(traverse and gyrostatic orientation survey) were used to improve the measurement accuracy. The results showed that the chose of survey instrument and survey technology and data processing method applied could ensure holing-through in a auxiliary shaft. The accuracy of the 14 km holing-through project reached an error of -0.182 m in the horizontal direction and an error of 0.125 m in an elevation direction.
作者 李英 单伟 Li Ying;Shan Wei(ORDOS Vocational College,ORDOS Inner Mongolia 017000,China;Shendong Geology and Survey Company,Yulin 719000,China)
出处 《矿山测量》 2019年第5期58-61,71,共5页 Mine Surveying
基金 鄂尔多斯职业学院科研基金项目(EJY1503) 科技支撑课题航空遥感数据自动处理与加工技术框架与规范研究(2011BAH12B01)
关键词 贯通测量 误差定权 误差预计 严密平差 Holing-through survey value of measurement error through forecast error rigorous adjustment
  • 相关文献

参考文献12

二级参考文献50

共引文献100

同被引文献34

引证文献5

二级引证文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部