摘要
针对济南轨道交通全自动运行项目对于车辆段土建预留方案的讨论,分析停车列检库线设置长度的考虑因素及原理,提出库线信号系统典型的轨旁设备布置方案。为全自动车辆段项目库线的长度确定和轨旁设备布置提供参考。
Aiming at the discussion of civil engineering reservation schemes for depots in Jinan Rail Transit Fully Automatic Operation Project, this paper analyses the factors and principles of the length of parking track, and puts forward a typical layout scheme of trackside equipment for the signal system of the parking track. It provides a reference for the determination of the length of the parking track and the layout of the trackside equipment in the fully automatic depot.
作者
董洪卫
Dong Hongwei(CRSC Research & Design Institute Group Co., Ltd, Beijing 100070, China)
出处
《铁路通信信号工程技术》
2019年第10期13-16,共4页
Railway Signalling & Communication Engineering
关键词
全自动车辆段
信号
设备布置
分析
fully automatic depot
signal equipment layout
analysis