结合哈尔滨地铁3号线二期工程进乡街站的现场情况,对施工过程中的方案优化进行了总结。为了响应哈尔滨市“还路于民,缓堵保畅”的号召,项目部根据现场情况,通过优化深基坑开挖施工方案,合理缩短了施工工期。
This paper summarizes the schemes optimization in the construction of Jinxiang Street Station of Phase II Project of Harbin Metro Line 3.In order to respond to the call of"returning roads to people,easing blockage and maintaining smooth"in Harbin,the project department has reasonably shortened the construction period by optimizing the construction scheme of deep foundation pit excavation according to the site conditions.
作者
仲军
管善志
ZHONG Jun;GUAN Shan-zhi(China Communications 2nd Navigation Bureau 3rd Engineering Co.Ltd.,Zhenjiang 212000,China)
出处
《工程建设与设计》
2019年第12期190-191,共2页
Construction & Design for Engineering
关键词
地铁车站深基坑
土方开挖
施工优化
deep foundation pit of metro station
earthwork excavation
construction optimization