期刊文献+

大宝山矿降低露天爆破震动对平硐影响的方法 被引量:2

Technology of reducing blasting vibration effect on adit in Dabaoshan open-pit mine
下载PDF
导出
摘要 以大宝山露天矿北部685平台下方存在640平硐为工程背景,分析了单响最大药量及起爆延时对爆破震动效应的影响;给出了深孔爆破设计方案,并预先在距炮孔底部50mm处采用沙包分离处理,形成空气间隔,且装药及填塞分类处理。现场试验表明,深孔爆破处理效果良好,640平硐稳定性并未受到不利影响。 Based on the background of 640 adit under the 685 platform in the north of Dabaoshan open-pit mine,the article analyzes the effect of the maximum dose of single hole and the initiation delay on the blasting vibration,gives the design scheme of deep hole blasting,the sand pack is divided into 50mm from the bottom of the hole in advance,air separation is formed,and the charge and packing are classified and processed.Field test shows that the deep hole blasting treatment is effective and the stability of the 640 adit is not affected.
作者 张兵兵 陈晶晶 张岗涛 韩振 王菲 方翔 ZHANG Bingbing;CHEN Jingjing;ZHANG Gangtao;HAN Zhen;WANG Fei;FANG Xiang(Guangdong Hongda Blasting Co.,Ltd.,Guangzhou 510623,China)
出处 《露天采矿技术》 CAS 2019年第3期62-64,共3页 Opencast Mining Technology
关键词 平硐 单响最大药量 起爆延时 爆破震动效应 深孔爆破 adit maximum dose of single hole initiation delay blasting vibration effect deep hole blasting
  • 相关文献

参考文献15

二级参考文献69

共引文献89

同被引文献8

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部