摘要
土压平衡顶管是顶管施工的一种重要施工方式,但如何将挖掘出的渣土从顶管机输送到地面,始终是顶管施工中的一项难题。长距离顶管干泥泵送施工工艺,就是一种将土压平衡顶管掘进机掘出的干泥改良为含水率65%~85%的塑态泥土,再连续泵送到地面的施工方法,实现了顶管施工干泥的长距离或超长距离的连续输送,具有较高的推广应用价值。
The earth pressure balancing pipe jacking is an important construction method in pipe jacking construction, but how to transport excavated dregs from pipe jacking machine to ground is always a difficult problem in pipe jacking con struction. The long-dista nee pipe jacking dry mud pumping constructio n tech no logy is a construction method to improve the dry mud excavated by the earth pressure balancing pipe jacking machine into the plastic mud with moisture content of 65%.85% and continuously to pump it to the ground, which realizes the Iong-distanee or super-long-distanee continuous transportation of dry mud in pipe jacking construction, and has high popularization and application value.
作者
张立新
ZHANG Lixin(Shanghai Civil Engineering Co., Ltd. of CREC, Shanghai 200436, China)
出处
《建筑施工》
2019年第3期505-507,共3页
Building Construction
关键词
长距离顶管
干泥
泵送
润滑减阻
long-distanee pipe jacking
dry mud
pumping
lubrication and drag reduction