摘要
赛尔六矿西二采区根据矿井验收要求,需要补掘一条采区轨道大巷534 m,工期短任务重,通过对岩巷施工工艺优化,采用快速成巷技术,提前8 d完成,并对应用效果进行分析和总结。
According to the acceptance requirements of the West Second Mining Area of Saier No.6Mine,it is necessary to drive a main track roadway with the length of534meters.Through the optimization of rapid excavation technics in rock drift,the rapid roadway construction technology was adopted,which was completed8days ahead of time.The application effects were also analyzed and summarized.
作者
卞学东
王庆国
BIAN Xue-dong;WANG Qing-guo(Xinjiang Saier Company,Xuzhou Mining Group,Tacheng,Xinjiang,834406)
出处
《煤炭科技》
2018年第4期89-91,共3页
Coal Science & Technology Magazine
关键词
岩巷
工艺优化
快速成巷
rock drift
process optimization
rapid roadway construction