新近吹填淤泥新型真空预压排水系统的研发 被引量:4

Research on new type drainage system of vacuum preloading technology for fresh hydraulic reclaimation silt
下载PDF
导出
摘要 新近吹填淤泥目前主要采用真空预压二次处理技术(浅层+深层)进行加固,施工成本较高、工期较长。基于新近吹填淤泥的真空固结机理,提出优化现行真空预压排水系统的新思路,依托广州港南沙港区三期工程软基处理II区工程,开展新型真空预压排水系统现场试验研究。结果表明,新近吹填淤泥经地基新型真空预压排水系统加固后,达到设计要求,解决了现行真空预压排水系统应用于新近吹填淤泥地基时所存在的排水板堵塞、真空压力传递效率低下等问题,且有效地缩短工期、节约成本;基于真空压力传递特性及最终加固效果,方案3 (原生料防淤堵型整体式排水板+专用接头+水平排水板+粉细砂垫层)更适用于新近吹填淤泥地基。 The two times treatment technology(shallow&depth)is used to reinforce the fresh hydraulic reclaimation silt foundation,and the construction cost is high and the duration is long.Based on the vacuum consolidation mechanism of fresh hydraulic reclaimation silt foundation,we put forward the new idea of optimizing the vacuum preloading drainage system.Based on Guangzhou Nansha port phase III relamation silt foundation improvement district II project,we study a new type of vacuum preloading and drainage system.The results show that fresh hydraulic reclaimation silt foundation which is reinforced by the new type vacuum preloading drainage system,can reach the design requirements.The new system solve the problem such as drainage plate to plug,vacuum pressure transfer efficiency low when traditional vacuum preloading drainage system is applied in fresh hydraulic reclaimation silt foundation,and can effectively shorten the time limit and save cost.Based on the characteristics of vacuum pressure transmission and final consolidation effect,scheme 3(the original raw materials of anti clogging type whole drainage plate+special joint+horizontal drainage plate+silty sand cushion)is more applicable to fresh hydraulic reclaimation silt foundation.
作者 杨茯苓 谢荣星 鲍树峰 余东华 YANG Fu-ling;XIE Rong-xing;BAO Shu-feng;YU Dong-hua(CCCC Fourth Harbor Engineering Co.,Ltd.,Guangzhou 510290,China;CCCC Fourth Harbor Engineering Institute Co.,Ltd.,Guangzhou 510230,China;CCCC Key Lab of Environmental Protection&Safety in Foundation Engineering of Transportation,Guangzhou 510230,China;The Fifth Engineering Company of CCCC Fourth Harbor Engineering Co.,Ltd.,Fuzhou 350008,China)
出处 《水运工程》 北大核心 2018年第11期179-186,共8页 Port & Waterway Engineering
关键词 新近吹填淤泥 新型真空预压排水系统 工艺研发 fresh hydraulic reclaimation silt new type drainage system of vacuum preloading technology process research and development
  • 相关文献

参考文献7

二级参考文献55

共引文献50

同被引文献26

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部