地铁建设项目具有占地面积大、土石方施工作业量多、开发周期长、环境影响范围广等特点,施工期极易造成水土流失。本文以深圳市地铁8号线一期工程为例,分析地铁施工期可能造成的水土流失危害,并提出防治对策,以供参考。
Metro construction project has the characteristics of large occupied area,excessive earthwork construction workload,long development cycle,wide environmental impact scope,water and soil loss erosion can be easily caused as well during construction.In the paper,stage I project of metro line 8 in Shenzhen is adopted as an example for analyzing water and soil loss erosion hazard caused during metro construction period,countermeasures are proposed as reference.
作者
储召蒙
CHU Zhaomeng(Shenzhen Yantian Flood Control and Drainage Facility Management Office,Shenzhen 518083,China)
出处
《水资源开发与管理》
2018年第1期39-41,共3页
Water Resources Development and Management
关键词
地铁项目
水土流失
危害及对策
metro project
water and soil erosion loss
hazard and countermeasures