摘要
本文以澳门外港新客运码头吹填工程水下沉管敷设为实例,介绍了水下沉管线路的选择,沉管的组成、组装、试浮、拖航、就位、下沉和挖泥船利用沉管施工的全过程。在各个环节,提出相应的技术要求和措施,保证了沉管敷设工的顺利进行。
Taking the reclamation project in Macao as an example, this paper make detailed description on the whole process of laying works, including the sele ction of pipe line, fabrication of pipes, test floating, towing, positioning, sinkings and at last,putting the pipe line into operation for the dredger. At every impor-tant link, there presented technical requirements and relevant measures, so as to make the laying work to be carried out successfully.