摘要
漫松引水 2 #洞为斜井施工标段。在进场晚、工期紧、单面距离长的不利条件下 ,成功地解决了长隧洞通风排烟这一难题 。
Mansong No.2 water gallery is classified as the Inclined Shaft Bid Section.The hard core is successfully broken down for the long tunnel's ventilating and exhaust emission under the unfaworable conditions of the delayed moblization, stringent workperiod and longer haulage distance.This paper explains the ventilating and exhaust removing technology which makes use of air pumping as the principle method by means of the self made iron sheet tube in long tunnel.
出处
《石家庄铁道学院学报》
2002年第B08期83-85,共3页
Journal of Shijiazhuang Railway Institute