摘要 介绍了天钢3200m3高炉供配电系统及传动控制系统中主要电气设备及装置的安装方法,并阐述了电气设备的接地及安装质量。在进行电缆桥架安装敷设时注重电缆桥架的多项功能,把桥架做为电缆敷设时的着力点进行施工设计。 The main electric equipment of power supply and distribution system and drive control system for 3 200 m3 BF and the installation method are introduced, and the grounding of electric equipment and installation quality expounded. Paying attention to the multifunction of the cable tray during laying and regarding the cable tray as the focus of laying during designing ensure the erection quality and apparent quality.
出处 《天津冶金》 CAS 2007年第S1期176-179,188,共5页 Tianjin Metallurgy
关键词 主控楼 盘柜 电缆 敷设 接地系统 质量 安装 main control building cabinet and board cable laying grounding system quality installation