通过对某高层建筑出现的倾斜问题,采用筏形基础以下补大直径(1.2 m)人工挖孔灌注桩提供顶升反力对该高层建筑纠偏,推动纠偏技术的发展,对进一步研究多高层建筑的纠偏提供了工程参考。
Through the inclined problem of a high rise building, using the filling pile with large diameter( 1.2m) under the raft foundation to provide the top rise and reverse force to the high rise building, promote the development of the rectification technology, and provide a reference for the further study of the rectification of the multi and high and high buildings.
出处
《建筑技术开发》
2018年第18期88-90,共3页
Building Technology Development
关键词
筏板基础纠偏
人工挖孔灌注桩
同步顶升
raft foundation correction
manual digging pile