摘要
结合澳博路氹上葡京酒店工程中围堰C基坑钢板桩工程实例,介绍了深基坑中拉森钢板桩的施工工艺、施工顺序和垂直度的控制,并且分析了钢板桩漏水涌砂的原因,提出处理措施。
Based on the construction of steel sheet pile cofferdam engineering practice, this paper describes the construction technical, construction sequence and verticality control, and then analyzes the reason and treatment measures for sand gushing and sand leakage during the construction of Lassen steel sheet pile.
作者
王爱溪
刘光兵
刘朝
WANG Aixi;LIU Guangbing;LIU Zhao(The First Engineering Company of CCCC Fourth Harbor Engineering Co.,Ltd.,Guangzhou Guangdong 510310,China)
出处
《施工技术》
CAS
2018年第19期75-77,115,共4页
Construction Technology
关键词
深基坑
围堰
拉森钢板桩
垂直度
施工技术
deep foundation excavation
cofferdam
Larsen steel sheet pile
verticality
construction