以太原市双塔北路改造为例,通过对其现状情况及周边太原站东广场及缓洪池的规划分析,发现双塔北路严重拥堵,且地处太原东山地区,一遇雨季便积水,市政配套管线老化等问题,在满足各规划规范的基础上,提出了现状管线改迁的施工组织方案,优化设计,为道路下穿地道的实施提供了条件。
Taking the reconstruction of Shuangta North road in Taiyuan city as an example,through the current situation and the planning and analysis of the surrounding Taiyuan station East square,this paper finds that the Shuangta North road is seriously congested and is located in the Dongshan area of Taiyuan,which will accumulate water during the rainy season. On the basis of meeting the various planning standards,the construction organization plan of the current situation pipeline relocation was put forward,and the optimal design was put forward,which provided the conditions for the implementation of downward channel under the road.