高墩现浇箱梁0号块托架设计及施工技术 被引量:2

Design and Construction Technology of Block 0 bracket for High Pier Cast-in-place
下载PDF
导出
摘要 结合在建的武汉城市圈孝感段汉江特大桥(105+180+105)m现场实际施工流程,介绍了一种高墩0号块托架的施工技术,主要包括钢板预埋,托架搭设,千斤顶反拉预压,预拱度设置及底模调整。实践证明,该施工方法简单、安全有效,尤其是千斤顶反拉预压技术减少了类似钢绞线、砂袋预压的繁杂工序,有利于节约工期成本。 In this paper, combining with the construction of wuhan city circle xiaogan period of the han river bridge(105 + 180 + 105) m the actual construction process, introduces a kind of high pier no.0 block bracket construction technology, mainly including steel embedded, bracket set jack counter loop preloading, camber setting and bottom die adjustment.It is proved by practice that the method is simple and safe and effective.In particular, the preloading technology of the jacking method reduces the complicated process of the preloading of similar steel wire and sand bags,which is beneficial to the saving of construction cost.
作者 田建家 徐碧 陈凌云 梁殷切 TIAN Jian-jia, XU Bi,CHEN Ling-yun, LIANG Yin-qie(Hubei luqiao group co. LTD, Wuhan, Hubei 430000, Chin)
出处 《科技视界》 2018年第16期93-94,共2页 Science & Technology Vision
关键词 连续梁 0号块 托架 预压技术 预拱度 施工 Continuous beam No.O block Bracket Preloading technology Prestressing camber Construction
  • 引文网络
  • 相关文献

参考文献4

  • 1陈伟,钟铭..桥梁施工临时结构设计[M],2002.
  • 2刘东跃主编..施工临时支撑结构专项技术方案[M].沈阳:辽宁科学技术出版社,2013:545.
  • 3孙训方等编,孙训方,胡增强修订..材料力学 1[M].北京:高等教育出版社,1982:387.
  • 4邵旭东主编..桥梁工程[M].北京:人民交通出版社,2007:548.

同被引文献15

引证文献2

相关主题

;
使用帮助 返回顶部