摘要
介绍了焦化酚氰废水处理的工艺流程,对酚氰废水生化处理后氨氮浓度较高的问题进行了分析,并采取了改进措施,改进后氨氮浓度达到了设计要求。
The process of phenol-cynaide-containing waste water treatment in coking plants is introduced. The reasons for the high ammonia nitrogen concentration in waste water after bio-chemical treatment of phenol-cynaide-containing waste water are analyzed. Based on the analysis result, improvement measures are taken, after which the ammonia nitrogen concentration meets the design requirement.
作者
孙红艳
张成展
刘武镛
Sun Hongyan;Zhang Chengzhan;Liu Wuyong(Beiying Company,Benxi Iron & Steel Group,Benxi 117017,China;Supplier Management Department of Benxi Iron & Steel Group,Benxi 117000,China)
出处
《燃料与化工》
2018年第4期49-50,共2页
Fuel & Chemical Processes
关键词
酚氰废水
生化处理
氨氮浓度
Phenol-cynaide-containing waste water
Bio-chemical treatment
Ammonia nitrogen concentration