摘要
通过对重载铁路运行的C96型30t轴重新型车辆与25 t轴重以下通用型敞车部件组成、尺寸、材质等方面的对比分析、研究,结合最新检修工艺流程、工装设备配置情况,论述日照南车辆段作为重载铁路车辆段,应以C96型30 t轴重车辆的检修为主,兼顾25 t轴重以下车型的检修。确定新建30 t轴重车辆段总平面布局及检修工艺方案,在工艺设计、工装设备配置上充分考虑30 t轴重车辆检修工艺的适应性,以满足各种车型的检修需求。
Through the composition,analysis and study of the heavy haul railway C96 30 t axis vehicles and the general vehicles bellow 25 t axle load in terms of the parts,size,material and other aspects and in view of new repair process and equipment configuration,this paper concludes that the Rizhao South Vehicle Depot as a heavy haul railway depot should focuses on the overhaul of C96 30 t axle load vehicle and that of the vehicle less than 25 t axle load. New 30 t axle depot layout and maintenance process scheme are defined,and process design and equipment configuration are addressed in the light of 30 t axle load vehicle maintenance process adaptability to meet the needs of the overhaul of various vehicles.
作者
何勇
HE Yong(Mechanical Power Design and Research Institute,China Railway Engineering Consulting Group Co.,L td.,Beijing 100055,China)
出处
《铁道标准设计》
北大核心
2018年第8期174-177,共4页
Railway Standard Design