鞍钢2580 m^3高炉大修开炉达产实践 被引量:3

Practice of Blowing-in and Reaching Design Capacity of the 2580 m^3 BF of Ansteel after Heavy Maintenance
下载PDF
导出
摘要 对鞍钢股份有限公司炼铁总厂2580 m^3高炉大修开炉达产实践经验进行了总结。本次高炉停炉大修68天后开炉送风,通过开炉前的精心准备,制定科学的开炉方案,首次尝试全风口操作的送风方式,顺利开炉,用时不到2天达产达效。 The operation practice of reaching the design capacity of the 2580 m^3 BF in General Ironmaking Plant of Angang Steel Co., Ltd. after its restart-up when finishing the heavy maintenance was summarized. The BF blowing -in was in operation after the 68 -day heavy maintenance. Thanks to the well -prepared work and the scientific scheme for blowing -in, the happy blowing-in was achieved by making the first attempt of supplying hot air through all the tuyeres. Therefore it took only 2 days to reach the design capacity.
作者 姜庆喜 范振夫 刘和 田景长 孟凡双 Jiang Qingxi;Fan Zhenfu;Liu He;Tian Jingchang;Meng Fanshuang(General Ironmaking Plant of Angang Steel Co.,Ltd.,Anshan 114021,Liaoning,China)
出处 《鞍钢技术》 CAS 2018年第4期48-51,共4页 Angang Technology
关键词 高炉 大修 开炉 全风口 达产 blast furnace heavy maintenance blowing-in all tuyeres reaching design
  • 相关文献

参考文献2

共引文献19

同被引文献20

引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部