针对出厂试验中某500kV变压器长时感应耐压试验局部放电量超标的情况,采用多端子测量法将局部放电源定位在高压套管上,对故障套管进行了分析与处理。
According to the situation of partial discharge exceeded in a 500 kV transformer,the partial discharge source is located in the high voltage bushing with multi-terminal measurement method. The fault is analysed and treated.
作者
邱欣杰
王刘芳
丁国成
尹睿涵
吴兴旺
QIU Xin-jie, WANG Liu-fang, DING Guo-cheng, YIN Rui-han, WU Xing-wang(Electric Power Research Institute, State Grid Anhui Electric Power Company, Hefei 230022, Chin)
出处
《变压器》
北大核心
2018年第5期69-71,共3页
Transformer
关键词
高压套管
局部放电
气穴放电
High voltage bushing
Partial discharge
Cavitation discharge