基于优先原则的启发式算法在ZM项目中的应用

Application of Heuristic Algorithm Based on Priority Principle in ZM Project
下载PDF
导出
摘要 施工进度计划的科学编制及合理安排是项目进度管理的重要内容,是影响项目工期目标实现的关键环节。通过关键路径法得到ZM项目建设最短工期进度计划,再从资源约束的角度,采用启发式算法对项目进度计划重新进行调整和编制,得出资源配置最优的工期。 The scientific preparation and reasonable arrangement of construction schedule is an important content of project schedule management, and is the key link affecting the realization of the project schedule target.The critical path method to get the shortest time ZM project construction schedule, from the resource constraint perspective, using heuristic algorithm to re adjust and prepare the project schedule, the optimal allocation of resources in the construction period.
出处 《化工设计通讯》 CAS 2017年第12期242-243,共2页 Chemical Engineering Design Communications
关键词 项目进度 优先原则 启发式算法 优化模型 project schedule priority principle heuristic algorithm optimization model
  • 相关文献

参考文献5

  • 1李建平,王书平,宋娟等编著..现代项目进度管理[M].北京:机械工业出版社,2008:177.
  • 2刘伊生..工程项目进度计划与控制[M].北京:中国建筑工业出版社,2008:202.
  • 3卢向南主编..项目计划与控制[M].北京:机械工业出版社,2009:299.
  • 4何正文,刘人境,徐渝.基于随机活动工期的资源约束项目鲁棒性调度优化[J].系统工程理论与实践,2013,33(3):650-659. 被引量:18
  • 5任少峰..基于模糊关键链的港铁列车项目进度计划优化设计[D].吉林大学,2014:

二级参考文献19

  • 1Kolisch R, Padman R. An integrated survey of deterministic project scheduling[J]. Omega, 2001, 29(3): 249-272. 被引量:1
  • 2Herroelen W, Leus R. The construction of stable project baseline schedules[J]. European Journal of Operational Research, 2004, 156: 550-565. 被引量:1
  • 3Van de Vonder S, Demeulemeester E, Herroelen W, et al. The use of buffers in project management: The trade-off between stability and makespan[J]. International Journal of Production Economics, 2005, 97: 227-240. 被引量:1
  • 4Van de Vonder S, Demeulemeester E, Herroelen W, et al. The trade-off between stability and makespan in resource-constrained project scheduling[J]. International Journal of Production Research, 2006, 44(2): 215-236. 被引量:1
  • 5A1-Fawzan M A, Haouari M. A bi-objective model for robust resource-constrained project scheduling[J]. Inter- national Journal of Production Economics, 2005, 96: 175-187. 被引量:1
  • 6Lambrechts O, Demeulemeester E, Herroelen W. A tabu search procedure for developing robust predictive project schedules[J]. InternationM Journal of Production Economics, 2008, 111: 493-508. 被引量:1
  • 7Van de Vonder S, Demeulemeester E, Herroelen W. Proactive heuristic procedures for robust project scheduling: An experimental analysis[J]. European Journal of Operational Research, 2008, 189: 723-733. 被引量:1
  • 8Herroelen W, Leus R. Project scheduling under uncertainty: Survey and research potentials[J]. European Journal of Operational Research, 2005, 165: 289-306. 被引量:1
  • 9Elmaghraby S. Activity nets: A guided tour through some recent developments[J]. European Journal of Opera- tional Research, 1995, 82(3): 383-408. 被引量:1
  • 10Blazewicz J, Lenstra J K, Rinnooy Kan A H C. Scheduling subject to resource constraints: Classification and complexity[J]. Discrete Applied Mathematics, 1983, 5: 11-24. 被引量:1

共引文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部