摘要
某工程设计采用嵌入式型钢混凝土组合结构梁,在原设计图仅有型钢梁位置、配筋而没有节点详图的情况下,通过对节点进行深化设计,现场施工采用骨架成型二次就位整浇工艺,保证了型钢组合结构梁的施工质量,为今后同类工程的施工积累了经验。
A factory design adopted the embedded steel reinforced concrete composite structure beam,under the situation of original design only had steel beam position,reinforcement and no detailed nodes,through the deeply design to nodes,the construction site with skeleton forming secondary in place of pouring process,ensured the construction quality of steel composite structure beam,laid experience for future similar engineering construction.
出处
《山西建筑》
2017年第26期105-106,共2页
Shanxi Architecture
关键词
嵌入式型钢混凝土
组合结构梁
工艺技术
embedded steel reinforced concrete, composite structure beam, process technology