摘要
针对某110 k V全户内智能变电站原设计采用钢筋混凝土管桩基础时存在的问题,经现场分析,拟采用复合桩基方案,指出该加固措施实施效果良好,实测测量值远小于规范限值。采用的地基处理方案针对性较强,工程事故处理方案实用性、经济性均较好。
According to the problems of the reinforced concrete pipe pile foundation in some 100 k V household intelligent substation design,the paper adopts the composite pile foundation scheme with the site analysis,points out the consolidation measures has better implementation and the measured value is less than the regular limited value,adopts the better foundation treatment scheme with better practice and economy of the treatment scheme for the engineering accidents.
出处
《山西建筑》
2017年第25期89-90,共2页
Shanxi Architecture
关键词
变电站
桩基础
承载力
复合桩基
substation
pile foundation
loading capacity
composite pile foundation