地铁盾构区间线路纠偏及调线技术 被引量:2

Technology of Deviation Rectifying & Line Adjustment in the Metro Shield Construction
下载PDF
导出
摘要 在地铁盾构区间施工过程中,由于各种原因,盾构机常有发生偏离设计轴线超过规范允许值的情况,此时若不采取必要措施,将会对建筑限界、铺轨及设备安装等后续工作造成严重影响。在深圳地铁9号线某区间盾构施工中曾发生过盾构机低于设计轴线约1m的情况,本文通过具体实例对轴线偏离的过程、原因以及采取的措施等进行详细论述,供类似情况借鉴参考。 In the metro shield construction,it often occurs that the shield machine deviates the designed line and exceeds the specification. In this case,if necessary measures are not taken,it will bring serious effects to the succeeding work such as boundary line of tunnel,rail laying and equipment installation. In the metro shield construction of Shenzhen No.9 metro line,it once occurred that the shield machine lowed below the designed axis up to 1.0 meter. By means of concrete case,this passage discusses the procedure,cause of the deviation, and the measures taken detailedly,and hope that this case can provide lessons for the similar engineering.
作者 袁传旭
出处 《广东土木与建筑》 2017年第3期66-69,81,共5页 Guangdong Architecture Civil Engineering
关键词 地铁盾构 偏离 轴线 措施 metro shield deviation axis measure
  • 相关文献

参考文献1

  • 1竺维彬,鞠世健等著..复合地层中的盾构施工技术[M].北京:中国科学技术出版社,2006:247.

同被引文献6

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部