摘要
本文针对赵楼煤矿大埋深高地温矿井制冷能力不足的问题,通过对井下现场作业地点的实测数据及相关分析研究,尊重现场实际,采用了井下集中制冷降温系统和井口全风量降温制冷系统。通过现场实践,取得了较好的预期效果,有效解决了深部矿井的高温热害,保障了井下作业地点的安全生产,对类似地质条件下的矿井具有较强的借鉴意义。
This paper addresses the problem of Zhaolou coal mine deep high temperature mine refrigeration capacity, according to the measured data of the field working place and related research, respect the actual site, using the underground centralized cooling system and air cooling refrigeration system around the wellhead. Through the practice, and achieved good results expected, effective solution to the high temperature of deep mine victims, ensuring the safety of production sites, with a strong reference to the similar geological conditions.
出处
《煤矿现代化》
2017年第5期73-75,共3页
Coal Mine Modernization
关键词
深井
高地温
工作面
降温
deep wel
high temperature
working face
reducing temperature