通过分析泥沙对抽水蓄能电站的影响,从使用岸边库法、水库防沙排沙、进出水口防排沙、管理力度等方面,阐述了抽水蓄能电站泥沙的处理策略,从而保障抽水蓄能电站的正常运行。
By analyzing the influence of the mud and sand on the pumped storage power station,the paper illustrates the treatment strategies of the mud and sand in some pumped storage power station from the bank slope method,anti-sand and desilting of reservoir,anti-sand and desilting at entrance and exit,and management,so as to ensure the operation of the power station.
出处
《山西建筑》
2016年第35期128-129,共2页
Shanxi Architecture
关键词
抽水蓄能电站
泥沙
水库
电力系统
pumped storage power station
mud and sand
reservoir
power system