摘要
结合老虎口大桥悬臂施工0号块施工情况,介绍了3~6号墩连续梁悬臂浇筑0号块施工的托架、临时支座、模板、混凝土浇筑等施工工艺及质量控制措施,以期为同类型桥梁施工奠定基础.
This paper combined with the construction of No.0 cantilever bridge construction block tiger mouth, combined with the work practice, introduces the 3-6 pier continuous beam cantilever construction of the No.0 block, temporary support bracket, template, concrete pouring construction technology and quality control measures, in order to lay the foundation for the same type of bridge construction.
出处
《建筑技术开发》
2016年第11期135-136,共2页
Building Technology Development
关键词
连续梁
悬灌施工技术
永久支座
临时支座
continuous beam
suspension irrigation construction technology
permanent support
temporary support