根据襄樊电厂2号汽轮机首次大修前后的试验情况,分析了大修前机组运行热耗偏高的原因,并提出了大修改进建议,对机组性能的改进进行了比较分析。
According to the testing data of No.2turbine units in XiangFan Power Plant,This paper analyzes the cause of higher running heat rate of the turbine unit before overhaul and makes suggestions on the Overhaul of the tur -bine unit,the improvement on the performance before and after overhaul was analyzed.
出处
《华中电力》
2002年第4期8-10,30,共4页
Central China Electric Power
关键词
大修
300MW汽轮机组
性能改进
试验
turbine unit
overhaul
efficiency of cylinder
performance test
heat rate