摘要
针对地基施工中遇粉砂土时,在基坑开挖过程中易形成流砂塌方现象而采取轻型井点降水措施。以枣泉电厂场地平整及地基处理工程1号汽机房基坑开挖为例,叙述轻型井点降水方案设计及具体的施工过程。
In this paper,the light well point dewatering measures in the process of foundation pit excavation are easy to form flow sand collapse phenomenon in the process of foundation construction.In Zaoquan power leveling the ground and foundation treatment engineering 1#turbine foundation pit excavation for example,describes the light well point dewatering design and concrete construction process.
出处
《建筑技术开发》
2016年第9期28-29,共2页
Building Technology Development
关键词
轻型井点降水
粉砂土
基坑
light well point precipitation
silty soil
foundation