摘要
鉴于古田溪一级水电站改扩建工程因施工现场地理条件复杂等诸多因素影响,施工工期滞后较多,而施工现场布置的起重设备无法满足机组大型预埋部件的吊装要求,为抢回滞后的工期,确保工程进度,因地制宜设计制作"自制吊架"进行机组预埋件的吊装,取得了预期的效果。
Ⅰn the renovation and expansion work of Gutianxi Ⅰ Hydropower Station,the construction is far behind the schedule because of the complicated geographic conditions. Furthermore,the lifting devices arranged in the construction area are not suitable for the lifting installation of the pre-embedded unit parts. Therefore,a handmade lifting gear is designed and built. The lifting installation work is successfully accomplished.
作者
林秉良
LIN Binliang(Gutianxi Hydropower Plant, Huadian Fuxin Energy Co. , Ltd. , Gutian 352258, Chin)
出处
《水电与新能源》
2016年第10期18-19,52,共3页
Hydropower and New Energy
关键词
尾水肘管
井字吊架
吊装
调整
draft tube elbow
double-cross shaped lifting gear
lifting installation
adjustment