Atay水电站二级坝左岸坝肩覆盖层帷幕灌浆设计

Overburden Curtain Grouting Design for Left-Bank Abutment of The Second Stage Dam of Atay Hydropower Project
下载PDF
导出
摘要 Atay水电站二级坝左岸堆石坝段及上坝公路段覆盖层岩性为粉质黏土混碎石、块石,经综合分析覆盖层帷幕灌浆现场生产性试验成果,提出了防渗帷幕设计方案并付诸实施,经三年多时间的运行,证明覆盖层的防渗设计是成功的。 The overburden layers of the rock-fill dam section on the left bank and of dam abutment of the second stage dam of Atay Hydropower Project consist of silty clay sandwiched with debris and rock block. According to the comprehensive analysis of the productive test results of site overburden curtain grouting, an impervious curtain design scheme is proposed and put into implementation. After operation of more than three years, the impervious design of overburden layer is proved to be successful.
作者 梁良 蒋永红
出处 《红水河》 2016年第5期58-60,共3页 Hongshui River
关键词 Atay水电站 帷幕灌浆 坝肩 覆盖层 Atay Hydropower Project curtain grouting dam abutment overburden layer
  • 相关文献

参考文献2

二级参考文献1

  • 1李茂芳 孙钊.大坝基础灌浆[M].北京:水利电力出版社,1987.. 被引量:15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部