摘要
以兰新铁路祁连山第二双线段为例,通过对碎屑流地层特殊地质的分析研究,积极探索了碎屑流地层铁路隧道的施工技术,找到了解决方法,并且对这种特殊地质下的铁路隧道施工有了一套相对完善的施工技巧和方法,填补了国内在碎屑流地层中大断面铁路施工时的技术空白。
Lan Xin railway Qilian Mountain, the second pair of line segments, for example by of debris flow formation special geological analysis and research, actively explore the debris flow formation of railway tunnel construction technology, found a solution, and a relatively perfect construction technique and method of this special geological railway tunnel construction, to fill the domestic in the debris flow formation in large section railway construction technology gaps.
出处
《湖南城市学院学报(自然科学版)》
CAS
2016年第5期15-16,共2页
Journal of Hunan City University:Natural Science
关键词
碎屑流
大断面
铁路建设
隧道施工
Debris flow
Large section
Railway construction
Tunnel construction