622.5MW亚临界火电机组主蒸汽再热蒸汽管道水压试验支吊点应力研究

Force-analysis on the Main Steam And Reheat Steam's Support and Hanger Point in Hydraulic Pressure Test Condition for 622.5 MW Subcritical Unit
下载PDF
导出
摘要 对一台622.5 MW亚临界机组主蒸汽、再热蒸汽及高低压旁路管道进行应力计算,并分析比较了热态、冷态及水压试验工况下支吊架受力以及设计结构荷载。研究结果表明:主蒸汽、再热蒸汽及旁路管道在水压试验工况下部分支吊架荷载由于水重影响增加较多,考虑到临时加固较为复杂,焊缝质量检测最好通过100%无损探伤完成;刚性支吊架设计时不宜考虑水压工况水重;若需进行水压试验,支吊架应根据水压工况与结构荷载并结合厂家提供的弹簧锁定工况承重荷载来综合考虑采取加固措施。 Stress analysis has been taken for the main steam, reheat steam and the bypass piping and the comparison also has been made among the work, cold and hydraulic pressure test condition, including the structure load. The conclusion of the study indicates that the hydraulic pressure test has a large influence on the piping load and it is better to examine the welding work by 100 % flaw detection; Hydraulic pressure test shall not be considered in the rigid hanger and support design; If the hydraulic pressure test is required, the hanger and support should be reinforced according to the hydraulic pressure test condition load, structure load and the manufacturer allowed load when spring is locked.
出处 《广东化工》 CAS 2016年第17期179-180,共2页 Guangdong Chemical Industry
关键词 主蒸汽 再热蒸汽 高低压旁路 水压试验 应力计算 main steam reheat steam HP/LP bypass hydraulic pressure test stress analysis
  • 相关文献

参考文献6

二级参考文献5

  • 1电力工业部.电力建设施工及验收技术规范(锅炉机组篇)[S].中国电力出版社,1996.. 被引量:2
  • 2DL/T5054-1996.火力发电厂汽水管道设计技术规定[S].[S].,.. 被引量:66
  • 3SDGJ6—90.火力发电厂汽水管道应力计算技术规定[S].[S].,.. 被引量:1
  • 4DL5031—1994.电力建设施工及验收技术规范:管道篇[S].[S].,.. 被引量:1
  • 5DL/T616-1997.火力发电厂汽水管道与支吊架维修调整导则[S].[S].,.. 被引量:2

共引文献82

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部