摘要
抗浮稳定性为水池结构设计的重中之重,不同抗浮方案选择将会直接影响工程施工与造价。以某港口石化有限公司3万t/a硫磺回收及溶剂再生装置液硫池单元为例,分析研究了半地下式水池的抗浮稳定性影响因素及其设计方案选择。
The anti-floating stability is taken as the top priority in its structural design,and the selection of different anti-floating scheme will directly affect the engineering construction and cost. Taking for example the 3 million t/year sulfur recovery and solvent regeneration unit liquid sulfur pond unit of a Port Petrochemical Co.,Ltd.,the anti-floating stability of semi-underground water tank most widely used in the process and its scheme selection were analyzed and studied.
出处
《工程建设》
2016年第4期40-43,共4页
Engineering Construction
关键词
水池
抗浮稳定性
影响因素
设计方案
water pond
anti-floating stability
influencing factor
design scheme