摘要 基于概率积分法地表任意点移动变形预计基本原理以及动态预计模型,结合研究区地质采矿条件,进行研究区不同阶段的地表移动变形预计分析。结合高压线塔和地下工作面的关系及研究区地表移动变形预计结果进行高压线塔处不同阶段的地表移动变形预计,与高压输电线路运行标准进行对比,分析实验区高压线塔的安全性,完成预计研究,并在开采期间定期开展巡线工作,确保线路安全运行。结果表明:通过概率积分法动态预计模型能够较好地完成矿区高压线塔不同阶段的移动变形预计研究,预计结果对实现矿区高压线塔的安全运行有一定指导作用。 Based on probability integral method and the moving deformation estimated,the basic principle of the surface arbitrary point and dynamic forecast model,combining the geological mining conditions in the study area,this study analyzed the results of surface movement deformation prediction in study area at different stages. Combining the relationship of pylons and the underground work face with the above results,this study analyzed the results of surface moving deformation prediction under the high voltage line towers at different stages.Then this study compared the results with transmission lines operating standards,analyzing the security of pylons to complete the expected research to ensure the safe operation of the line. And regular patrol work is necessary during mining. The results shows that probability integral method is better to complete the moving deformation prediction of high voltage line towers at different stages. And the results of prediction has a great guiding to the safe operation of pylons.
出处 《河南城建学院学报》 CAS 2016年第3期69-74,共6页 Journal of Henan University of Urban Construction
基金 国家自然科学基金重点项目(U1261206) 河南省高等学校重点科研项目(15A420005) 河南理工大学博士基金项目(B2012-004)
关键词 开采沉陷 高压线塔 概率积分法 移动变形预计 mining subsidence high voltage line towers probability integral method moving deformation prediction
  • 相关文献

参考文献18

二级参考文献135

共引文献165

同被引文献19

引证文献1

二级引证文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部